Addition Project at TBD
As a means of providing you with regular communication about the TBD Addition Project, this section of The Core will include a monthly update.
TBD Addition Project Need
Due to the increase in enrollment over the years, there is a need to add additional instructional space at TBD. The TBD Addition Project will address the special-area classes that are now on carts, the specialized classes without spaces, and the removal of the trailer, which was always intended to be a temporary structure.
Project Details
The TBD Addition Project will add four (4) full-size classrooms and two (2) small-group classrooms. Weaving together the existing interior and exterior aesthetic and architectural elements, this Addition Project will run parallel to the current first-grade wing; however, it will not run the full length of the existing wing.
In addition to this project, two sets of student restrooms will be renovated, and the school boilers will be replaced inside TBD during the summer months.
Click to see the renderings, the aerial view, and the material boards for both the addition and bathroom projects.
Project Timeline
The TBD Addition Project was shared with the Old Tappan Planning Board in February and was approved by the Department of Education in March.
We awarded the bid to the lowest, responsible bidder, Vanas Construction Co., Inc., earlier this month. We approved a construction management company, Epic Management, to work with us for the duration of this project.
As you know, during April Break, the trailer was removed from the grounds.
On or about June 8, a construction fence will be erected around the construction site. Click to see the aerial view of the fence outline.
Construction will begin once school is dismissed in June. All inside work, such as the restroom renovations, will be completed during the summer months. The full Addition Project will run from the summer of 2026, through the 2026-2027 school year, and through the summer of 2027. Completion is anticipated for Back-to-School in September of 2027.
Project Impact
Starting in June, once the construction fence is erected, certain classrooms will be assigned different dismissal doors. If your child’s dismissal door will be affected, Ms. Boyce and the classroom teacher will let you know.
On behalf of the Board of Education, faculty, staff, and students, thank you to our supportive community for your commitment to our schools!